Before commit[80d17497b7 mdadm: improve the run-ptest],
the mdadm ptest just run some tests without
"--keep-going" option. After the option added in
commit 80d17497b7, all test cases have chance to
be called.
But the logic in mdadm upstream commit
[e2a8e9d tests: wait for complete rebuild in integrity checks]
will make the test enter infinite loop especially in
qemu env as commit e2a8e9d update the logic from
"check wait" to "check state 'U*'" for testcase
tests/01r5integ and tests/01raid6integ. Considering all
other cases still use "check wait" logic, so revert e2a8e9d
to make tests/01r5integ and tests/01raid6integ also use
"check wait" logic to avoid the infinite loop.
[YOCTO #13368]
Signed-off-by: Mingli Yu <Mingli.Yu@windriver.com>
Signed-off-by: Richard Purdie <richard.purdie@linuxfoundation.org>
|